Quantcast

PENNSYLVANIA RECORD

Saturday, November 2, 2024

Case of concrete worker injured on site of CHOP project coming to trial in Philly in the spring

State Court
Construction(1000)

PHILADELPHIA – A lawsuit from a concrete worker allegedly struck by a falling metal object on the job against the construction entities with ties to the Children’s Hospital of Philadelphia Schuylkill project is heading to trial next spring.

Per an updated case management order issued by Philadelphia County Court of Common Pleas Judge Denis Cohen on Sept. 3, a settlement conference in the case will take place on Dec. 2, followed by a tentative pre-trial conference date on March 2 and finally, a projected trial date of April 6, 2020.

Shawn Lichtfuss of Hatfield initially filed suit in the Philadelphia County Court of Common Pleas on Oct. 10, 2018 versus Berlin Steel Construction Company of Harrisburg, plus L.F. Driscoll Company, LLC of Erie, Tishman Construction Corporation of Pennsylvania of Harrisburg and Driscoll/Tishman, A Joint Venture of Bala Cynwyd (all collectively doing business as “Driscoll/Tishman, A Joint Venture”).

On Sept. 20, 2016, Lichtfuss said he was performing concrete installation and finishing at the CHOP Schuylkill construction site on behalf of his employer, Madison Construction Company. Directly above him on a higher floor, simultaneous project work was occurring through employees of defendant Berlin Steel Construction Company, the suit said.

The suit states Berlin Steel’s work was non-compliant with Occupational Health and Safety Administration (OSHA) regulations.

“Plaintiff Shawn Lichtfuss was on his hands and knees performing concrete work on the first floor of the project job site, when he, suddenly and without warning, was violently struck in the head by a metal object that had fallen from overhead. Immediately after the incident, Lichtfuss saw a metal object/tool laying on the ground next to him that was not there prior to him being struck,” according to the lawsuit.

Lichtfuss allegedly received a host of injuries in the accident, including herniation at his C3-C4 vertebrae and bulges at his C5-C-7 vertebrae confirmed by MRI requiring multiple intralaminal epidural steroid injections, bilateral facet joint injections, medial branch radiofrequency ablations and future surgical repair, bilateral C6-C7 radiculopathy with active denervation confirmed by EMG, cerebral concussion, post-concussive symptoms consistent with trauma to the head/neck region, sprain and strain of his entire spine, bilateral shoulders and left wrist, post-traumatic headaches and a severe and permanent shock to his nervous system.

In November, the construction companies involved at issue filed an answer that discounted liability from themselves for Lichtfuss’s injuries.  

On Oct. 18, 2018, counsel representing all parties mutually stipulated that “all allegations of gross negligence and/or recklessness and all demands for punitive and/or exemplary damages are hereby dismissed from plaintiff’s complaint without prejudice.”

For multiple counts of negligence, the plaintiff is seeking damages in excess of $50,000, jointly and/or severally, consisting of compensatory damages, delay damages, interest and costs of suit.

The plaintiff is represented by Fredric S. Karpf of Hoffman Sternberg & Karpf, in Southampton.

The defendants are represented by Michelle D. Coburn and Monica T. Nugent of White & Williams, in Philadelphia.

Philadelphia County Court of Common Pleas case 180703940

From the Pennsylvania Record: Reach Courts Reporter Nicholas Malfitano at nick.malfitano@therecordinc.com

More News